Manor River West

Manor West River

Location: Tampa, Florida

Award: Lower Carbon Concrete

Project Team

Owner: Tampa Housing Authority

Contractor: Balfour Beatty

Architect: MSA Architects

Engineer: McNamara/Salvia Structural Engineers

Concrete: Maschmeyer Concrete Company

Slag Cement: Argos

Located in Tampa, FL, USA, this multi-family project is currently under construction in the West River neighborhood along the Hillsborough River. The complex will feature an eight-story mid-rise apartment building with 360 units, high-end finishes, and amenities including a pool, fitness center, and clubhouse. The project will also include an eight-level parking garage with 530 parking spaces.

Slag cement was selected for the concrete mixture, to increase its pumpability, workability, and durability as well as provide a low carbon mixture. The mixture provided the contractor with adequate workability and setting times, and it met strength requirements.

Application Type

Application TypeFoundations
% Slag Cement Replacement50%
% Portland Cement
% Portland Limestone Cement50%
% Other SCM (if applicable)
AggregateNo. 57 limestone
Water/cement ratio0.42
7-day strengths5,700 psi
28-day strengths7,710 psi
Application TypeColumns
% Slag Cement Replacement50%
% Portland Cement
% Portland Limestone Cement50%
% Other SCM (if applicable)
AggregateNo. 89 limestone
Water/cement ratio0.42
7-day strengths6,740 psi
28-day strengths9,280 psi
Application TypeShear Walls
% Slag Cement Replacement50%
% Portland Cement
% Portland Limestone Cement50%
% Other SCM (if applicable)
AggregateNo. 89 limestone
Water/cement ratio0.35
7-day strengths8,040 psi
28-day strengths10,350 psi

Source: https://www.slagcement.org/post/manor-west-river